Defining SPM acceptance criteria

Acceptance criteria decide when a machine is finished. Agreed before the build, they are a specification both sides design toward. Agreed afterwards, they become an argument conducted under pressure, usually while production waits.

7 min read · Last reviewed 28 September 2026 · All resources

01

Rate, stated unambiguously

A rate needs a basis. Parts per hour at a steady state is different from parts per shift including changeovers, breaks and the occasional jam — sometimes by a wide margin.

State which you mean, over what period, and whether planned stoppages count. Most rate disputes are definitional rather than technical.

02

Quality, on the characteristics the machine controls

A machine can only be held to features it actually produces. Incoming variation in the blank, or a characteristic created by a prior operation, is not the machine's to guarantee.

List the characteristics the machine controls, the tolerance on each, and the measurement method. Agreeing how something is measured prevents two correct measurements disagreeing.

03

Run length and repeatability

  • How many consecutive parts constitute the demonstration
  • Whether the run must be uninterrupted, and what counts as an interruption
  • How many parts are measured, and to what sampling plan
  • Whether the run is repeated on a different shift or by a different operator
04

State the conditions

A machine demonstrating rate and quality on hand-picked blanks, with the supplier's engineer operating it, is not the same as the same machine on your material with your operator.

Specify the material, who operates it, and where the demonstration happens — at the builder's works, at yours, or both. Two-stage acceptance is common and reasonable.

05

Agree what happens on failure

  • How long the builder has to correct a shortfall, and how many attempts
  • Whether partial acceptance is possible if rate is met but quality is marginal
  • How payment relates to acceptance stages
  • What happens if a criterion turns out to be unachievable for a reason outside the builder's control
06

Define the handover, not just the machine

  • Documentation: drawings, parts lists, electrical schematics, operating and maintenance instructions
  • Spares supplied, and the recommended holding list with lead times
  • Training for operators and for maintenance, and how many people
  • Support arrangements after acceptance, and for how long

FAQ

Frequently asked questions

The questions engineers and buyers ask before sending a drawing. If yours is not here, ask it directly — you will get an engineer's answer, not a brochure.

Still have a question?

Talk to Anita M.N, Managing Partner, or send the drawing and let the review answer it.

Who should write the acceptance criteria?

Both parties, jointly. The buyer knows what the machine must achieve; the builder knows what is measurable and controllable. Criteria written by one side alone tend to be either untestable or unachievable.

Is acceptance at the builder's works enough?

It is a useful first stage but rarely sufficient on its own. Conditions at your site — material, operators, services, environment — differ, which is why two-stage acceptance is common.

What if we disagree about whether a criterion was met?

That is what the agreed measurement method is for. If it was not agreed in advance, both parties can measure correctly and reach different conclusions.

Should acceptance include a period of production?

For a machine you depend on, a short production period after installation surfaces problems a demonstration run will not. It needs to be defined carefully so it does not become open-ended.

Start a project

Send us your drawing, sample or problem statement

Share what you are trying to make or fix. Our engineering team reviews every enquiry and responds with the questions that matter, a feasibility view and next steps.

Prefer to talk?

Call or WhatsApp Anita M.N, Managing Partner.