Define the boundaries before you time anything
Last good part to first good part is the definition worth using, because it includes the first-off inspection and any adjustment that follows it. Those are real, they are variable, and they are where a surprising share of the time goes.
A baseline measured any other way will be contradicted the first time someone on the shop floor disagrees with it, and the improvement project loses credibility before it starts.